155. §

155. §

1. The Public Procurement Arbitration Board may order that certain cases being dealt with by it be consolidated if their subjects are interrelated or settling such cases collectively is justified by practical, economic or other procedural considerations.

2. The Public Procurement Arbitration Board may order that certain parts or elements of application of a given case being dealt with by it be separated if settling such cases separately is justified by practical, economic or other procedural considerations.

3. In case the applicant has more issues (elements) in the application concerning the same procurement procedure the Public Procurement Arbitration Board may make its decision at the same time. The Public Procurement Arbitration Board may make a single compound decision.